Pre-Construction Risk Review
[ RISK REVIEW TOOL ]

Pre-Construction Scope Gap Identifier

Check every item that applies to your project. Items you flag will appear in a risk-prioritized scope summary — the same categories Rockin J Works reviews in a formal Pre-Construction Risk Review engagement.

[ FLAGGED ITEMS ]
HIGH RISK
0
MEDIUM RISK
0
LOW RISK
0
TOTAL FLAGGED0
MEP coordination drawings not included in permit setHIGH RISK

Mechanical, electrical, and plumbing systems require coordination drawings to prevent field conflicts. Missing from bid set = guaranteed RFIs and change orders.

Structural penetrations not shown on architectural drawingsHIGH RISK

Any penetrations through rated walls or structural members must be detailed before bid. GCs will exclude or price high if not shown.

Fire alarm/sprinkler coordination with new ceiling layoutMEDIUM RISK

Relocated ceilings require sprinkler head relocation. If not shown in bid set, expect a significant change order post-contract.

Electrical panel capacity not verified for new loadsHIGH RISK

Tenant improvements often add significant electrical load. Panel capacity must be confirmed before bid or GC will exclude.

OFE list not included in bid documentsHIGH RISK

Any equipment furnished by owner but installed by GC must be listed with rough-in requirements. Missing = scope gaps and coordination failures.

Utility rough-in requirements for OFE not specifiedMEDIUM RISK

Each piece of owner-furnished equipment needs specific utility connections. These must be in the bid set for accurate GC pricing.

Delivery and installation sequence not coordinatedLOW RISK

OFE delivery timing must align with GC schedule. Late delivery = schedule delays and potential liquidated damages.

Deferred submittals not listed in permit documentsHIGH RISK

Items approved for deferred submittal (fire suppression, structural, etc.) must be listed. Unlisted deferred submittals cause permit delays.

Deferred submittal timeline not establishedMEDIUM RISK

Without a timeline for deferred submittals, GC cannot sequence work properly. This is a common source of schedule slippage.

Fire suppression design not included in permit setMEDIUM RISK

Fire suppression is frequently deferred. Ensure the GC's bid includes the design-build cost or it will be a change order.

Switchgear / electrical gear lead times not accounted forHIGH RISK

Electrical switchgear can have 16-52 week lead times. If not ordered at contract execution, project will be delayed.

HVAC equipment lead times not confirmedHIGH RISK

Custom or commercial HVAC equipment can have 12-20 week lead times. Confirm before bid.

Specialty finishes / custom millwork lead timesMEDIUM RISK

Custom millwork and specialty finishes can have 8-16 week lead times. Must be ordered early or will delay substantial completion.

Elevator / lift equipment (if applicable)MEDIUM RISK

Elevator equipment typically requires 16-26 weeks. Must be included in early procurement schedule.

Ceiling height conflicts between trades not resolvedHIGH RISK

HVAC ductwork, electrical conduit, fire suppression, and structural all compete for ceiling space. Conflicts not resolved in design = field change orders.

Plumbing waste lines conflict with structural beamsHIGH RISK

Waste line routing through structural bays requires early coordination. Discovered in field = expensive structural modifications.

Exterior wall penetrations not coordinated with building envelopeMEDIUM RISK

Any penetrations through the building envelope require landlord approval and weatherproofing details. Often missed in TI scope.

IT/AV rough-in not included in electrical scopeLOW RISK

Low-voltage rough-in is frequently excluded from GC scope or priced as an allowance. Clarify before bid.

City of Dallas permit timeline not factored into scheduleMEDIUM RISK

Dallas permit review can take 4-12 weeks depending on project complexity. GC schedule must account for this.

Special inspections not identified in bid documentsMEDIUM RISK

Structural, concrete, and welding inspections require third-party special inspectors. Cost must be in bid or it's an owner cost.

Certificate of Occupancy requirements not confirmed with AHJLOW RISK

CO requirements vary by jurisdiction and occupancy type. Confirm with the Authority Having Jurisdiction before bid.